StayLive actively promotes the sharing of information as soon as possible after near miss or actual safety incidents to inform members about hazards arising out of their operations.
Following completion of works and site demobilisation, power outages were later advised to the team. On further inspection it was identified that a 400V cable which was not identified on any as built plans was damaged in two locations during the pull back of the ducts.