9 December 2025
During planned outages at our hydro power stations, several dewatering and rewatering operations are scheduled.
28 November 2025
A metering technician visited a commercial and industrial customer's premises to test and certify a CAT4 meter following site energisation.
6 October 2025
The use of a hook on a forklift as a crane.
6 October 2025
Timberlands running block fell approximately 36 metres from teh Earth Peak crossarm to ground level.
24 September 2025
Wind Farm sites can experience extremes in weather, quickly changing environmental conditions and steep and challenging topography.
19 September 2025
A tank underwent internal inspection and minor repairs, requiring material removal and disposal in a re-purposed ISO Container.
23 July 2025
A worker was electrical testing the workshop appliances. When plugging in a large grinder to test it, the grinder instantly started up and took off.
11 July 2025
A new screen cleaner and intake screens were being installed at the intake forebay on the canal.
17 June 2025
From 9th June 2025, BOC are introducing an increased pressure and capacity MP15 Nitrogen Cylinder (152MP15) in the North Island which will replace the existing G15 cylinders (152G15).
17 June 2025
During the commissioning of G2 11kV switchgear cubicle and circuit breaker, three tagged earthing leads were inadvertently left connected to the G2 11kV terminations on the Local Services Transformer.